Road Closure Map – August 2022

02/08/2022

Morlais Roadworks 2022 (Aug 22 update)_Cym August 1st 2022 Update; Porth Dafarch Road remains closed until 22nd August on current forecast to allow completion of section 4c. Once section 4c is complete, South Stack Road will be closed again to allow sections 4a and 4b to be constructed from late August through to late October. […]

Road Closure Map July – 2022

06/07/2022

  July 5th 2022 Update; South Stack Road is now open again following completion of the ducting in section 3a. Porth Dafarch Road will now be closed until late August to allow duct installations in sections 5a and 4c. South Stack Road will stay open through a large proportion of August. It will then shut […]

Road Closure Map – June 2022

09/06/2022

June 9th 2022 Update Road at section 3a is now closed for duct installation until mid July (subject to speed of construction), access for residents and businesses within closed sections will be maintained by our contractor Jones Bros. Residents and businesses on South Stack Road to the north of section 3a should use the signposted […]

Road Closure Map – May 2022

26/05/2022

    *Note: This map will be reviewed and updated bi-weekly, please check regularly for the most up to date map. 

Jones Brothers – Trenching

24/05/2022

Jones Brothers have completed 1.5KM of the trenching for the ducting and have 5km left to complete along South Stack Road.

Community Liaison Group

16/05/2022

The first meeting of the Morlais Community Liaison Group took place on the 9th of May at the Ucheldre Centre, Holyhead. Around 30 people attended from different community groups and interests. Former council Leader, Clive McGregor chaired the meeting with contributions from Gerallt Llewelyn Jones, Karen Jones both directors of Morlais giving an overview of […]

Jones Brothers – HDD & Trenching Works

12/05/2022

HDD Jones Brother are preparing to undertake Horizontal Directional Drilling in the Parc Cybi area near the Premier Inn Hotel. This work will begin on Wednesday the 11th of May and will continue for around 6-8wks. Trenching  Jones Brothers will begin trenching works on Plas Road, they are expecting to receive the delivery of the […]

Project Update -16th March 2022

16/03/2022

As part of the preliminary phase, contractors will be carrying out the following activity linked to Morlais over the coming weeks: Setting up a site office at the Holyhead Hotspur Compound Conducting a trial trench excavation at the football club car park If the trial is successful this work will continue in to the leisure […]