Road Closure Map – 22nd November 2022

22/11/2022

November 23rd 2022 Update; Section 1 (no closure required) started as planned in November and will continue to be controlled with a traffic light arrangement. This section has been delayed due to dealing with a culvert and some wet ground and is now expected to finish just before Christmas 2022. The South Stack Road closure […]

Road Closure Map – 25th October 2022

26/10/2022

  Section 1 (no closure required) is now planned for the start of November and will be controlled with a traffic light arrangement. The South Stack Road closure remains in section 2 to allow the ducts to be installed there. This closure will be until Christmas 2022 which also includes the installation of the cable […]

Road Closure Map – 10th October 2022

14/10/2022

October 10th 2022 Update; Sections 4a and 4b are now complete. The 4a and 4b South Stack Road closure has now moved to section 2 to allow the ducts to be installed there. This closure will be until Christmas 2022 which also includes the installation of the cable between JP1 and JP3. Access to local […]

Weekend Working

01/09/2022

Following the duct installations along Porth Dafarch Road taking longer than expected recently, Jones Brothers will be working for extended periods over the next two weekends on South Stack Road in order to mitigate the programme delay on the duct installations. The details are as follows;   Sat 3rd & Sun 4th Sept 22 (07:00 […]

Road Closure Map – September 2022

30/08/2022

  August 30th 2022 Update; Porth Dafarch Road works (4c) have been slower than expected so the road remains closed until early September. Once section 4c is complete, South Stack Road will be closed again from beginning of September to allow sections 4a and 4b to be constructed until early October. Please use the diversion […]

Road Closure Map – August 2022

02/08/2022

Morlais Roadworks 2022 (Aug 22 update)_Cym August 1st 2022 Update; Porth Dafarch Road remains closed until 22nd August on current forecast to allow completion of section 4c. Once section 4c is complete, South Stack Road will be closed again to allow sections 4a and 4b to be constructed from late August through to late October. […]

Road Closure Map July – 2022

06/07/2022

  July 5th 2022 Update; South Stack Road is now open again following completion of the ducting in section 3a. Porth Dafarch Road will now be closed until late August to allow duct installations in sections 5a and 4c. South Stack Road will stay open through a large proportion of August. It will then shut […]

Road Closure Map – June 2022

09/06/2022

June 9th 2022 Update Road at section 3a is now closed for duct installation until mid July (subject to speed of construction), access for residents and businesses within closed sections will be maintained by our contractor Jones Bros. Residents and businesses on South Stack Road to the north of section 3a should use the signposted […]

Road Closure Map – May 2022

26/05/2022

    *Note: This map will be reviewed and updated bi-weekly, please check regularly for the most up to date map. 

Jones Brothers – Trenching

24/05/2022

Jones Brothers have completed 1.5KM of the trenching for the ducting and have 5km left to complete along South Stack Road.