July 5th 2022 Update;
- South Stack Road is now open again following completion of the ducting in section 3a.
- Porth Dafarch Road will now be closed until late August to allow duct installations in sections 5a and 4c.
- South Stack Road will stay open through a large proportion of August. It will then shut again to allow sections 4a and 4b to be constructed through September and October.